HS2 unveils Crewe Link £1.6bn civils bid plan

HS2 has outlined plans to split the proposed West Midlands to Crewe section of the high speed railway into two civils contract packages.

Procurement chiefs said they are still keeping procurement options open with the possibility of running a competition between its four existing phase one joint venture contractors instead of a pre-qualifying a fresh field of bidders.

A current market testing exercise will help to inform the decision about which procurement route to take later next year.

The 39km southern section of the HS2a route is expected to cost up to £870m while the shorter 28km northern section including two short tunnels is estimated to cost up to £750m to build.

The procurement process could start by the third quarter of next year, with bids being invited in the first quarter of 2020, and the winning bidder announced by Spring 2021.

Design work for phase 2a is expected to begin next year, with construction scheduled to start as early as 2021

Article courtesy of Aaron Morby – Construction Enquirer

Read More

How to Stay Positive in an Uncertain World

In recent years, the simple act of flipping on the evening news has become a challenging experience for those of us who strive to maintain a positive attitude. Just sitting there in your living room, watching one upsetting news story … Continue reading

The Do’s and Dont’s of Video Interviews

Despite a hybrid return to the office, interviews continue to be conducted via video link as a first port of call followed by face to face second stage interviews. So, what can you do to ensure you are invited for … Continue reading

Archive