HS2 unveils Crewe Link £1.6bn civils bid plan

HS2 has outlined plans to split the proposed West Midlands to Crewe section of the high speed railway into two civils contract packages.

Procurement chiefs said they are still keeping procurement options open with the possibility of running a competition between its four existing phase one joint venture contractors instead of a pre-qualifying a fresh field of bidders.

A current market testing exercise will help to inform the decision about which procurement route to take later next year.

The 39km southern section of the HS2a route is expected to cost up to £870m while the shorter 28km northern section including two short tunnels is estimated to cost up to £750m to build.

The procurement process could start by the third quarter of next year, with bids being invited in the first quarter of 2020, and the winning bidder announced by Spring 2021.

Design work for phase 2a is expected to begin next year, with construction scheduled to start as early as 2021

Article courtesy of Aaron Morby – Construction Enquirer

Read More

How to stay motivated when job hunting?

An uncertain economic forecast is leading some companies to hold off on recruiting more staff and focus on keeping their existing employees. Despite this, overall job vacancies still remain above levels seen before the pandemic.  The construction sector is generally … Continue reading

Significant law changes comes into place in 2024 for Civil Engineers – mandatory integration of sustainable drainage systems (SuDS)

In 2024, significant changes are imminent for civil engineers in England. A new law will enforce the integration of sustainable drainage systems (SuDS) into new developments exceeding 100sq/m. This is outlined in Schedule 3 of the Flood and Water Management Act 2010. This … Continue reading

Archive